Finish a build

Say how many came out good. Materials are used and the pieces go into stock.

Manufacturing 5 steps Checked Nov 21, 2026

Finishing is the moment a build becomes real. What it used leaves your materials and stock, and the good pieces go onto the shelf at what they cost to make.

Before you start

Finishing moves stock and money, so it is switched off for everybody to begin with. An admin can finish a build, or can allow somebody else to.

Steps

  1. Open Make from the menu and choose Planned.
  2. Open the build and press Finish build.
  3. In Started, say how many were begun. Materials for that many are used.
  4. In Good pieces, say how many passed and go into stock.
  5. Press Finish and add to stock.

Pieces that did not make it

If fewer came out good than were started, the lost pieces share the cost of what was used. Each good piece then costs a little more, which is the true cost.

If you made fewer than planned

Start fewer than the build planned and a tick appears to keep the rest planned as a new build. Leave it on and the remainder stays on your list under its own number.

Lots, serial numbers and crew time

You are only asked for these when they apply:

  • Lot number and Best by, for a product followed by lot. The lot starts as the build's number.
  • Serial numbers, one for each good piece, for a product followed by serial number.
  • Crew hours, when your business counts crew time in what a build costs.

If you do not have enough

You cannot finish a build your materials or stock do not cover. You are told what is short. Receive or count it in first, or start fewer.

Made a mistake?

Open the finished build and press Undo build. The pieces come off the shelf, everything it used goes back, and the build returns to Planned. This only works while all of those pieces are still on the shelf.

Read next